The current estimated timescales for further progress are:

Ecology survey of disused line -  Spring 2011 - completed
Clearance of disused line        - Winter 2012/13 ??
GRIP 4 Design                       - October 2012 - July 2013
Funding Application and Decision .....????
GRIP 5 Plan                          - June - Dec 2015
GRIP 6 Build                         - Dec 2015 - end 2016
Line open                             - 2017